26kW Solar Installation at Anjana Chitra Mandir by SolarLogix
SolarLogix successfully designed and executed a 26 kW rooftop solar power plant for Anjana Chitra Mandir, a commercial cinema hall, located in Raniganj, West Bengal.
The project was implemented to reduce high daytime electricity consumption, optimise operational energy costs, and support the theatre’s transition towards clean and sustainable energy, while ensuring safe grid-compliant operation and long-term system reliability.
This installation serves as a reference rooftop solar project for cinema halls and entertainment venues in West Bengal.
📍 Project Details
| Parameter | Details |
|---|---|
| Client Name | Anjana Chitra Mandir |
| Industry | Commercial / Entertainment (Cinema Hall) |
| Location | Raniganj, West Bengal |
| Installed Capacity | 26 kW Rooftop Solar Plant |
| Structure Type | Customized Fabricated Rooftop Structure |
| Solar Modules | TATA Power Make Monoperc 500 Series Modules |
| Inverter Type | TATA Power Certified Solis String Inverter with MPPT |
| Grid Integration | Net Metering (Utility Liaisoning) |
| Safety Systems | Conventional Lightning Arrester |
| Maintenance Access | GI Walkways (Purlin-to-Purlin) |
| Monitoring | Remote Monitoring with Live Performance Feed |
| Insurance | TATA AIG Comprehensive Solar Plant Insurance |
⚙️ Engineering & Safety Highlights
The system was engineered with a strong focus on commercial safety, reliability, and compliance:
✔ Net-metered system for optimal utilisation of generated solar power
✔ Conventional lightning arrester for electrical surge protection
✔ Customized fabricated rooftop structure suitable for cinema buildings
✔ GI maintenance walkways ensuring safe long-term O&M access
✔ High-quality fasteners and foundation bolts for structural durability
✔ Remote monitoring system for real-time performance tracking
The design ensures safe operation, easy maintenance, and consistent energy generation.
⚡ Performance & Financial Impact
-
Specific Generation: ~1300 units per kW per year
-
Estimated Annual Generation: ~33,800 units
-
Applicable Grid Tariff: ₹8.5 / unit
-
Estimated Annual Savings: ~₹2.9 lakh
-
Payback Period: ~1 to 2 years
-
System Life: 25+ years
The solar plant significantly reduces grid electricity dependency, delivering fast payback and stable long-term savings for the cinema hall.
🌱 Environmental Impact
This 26 kW rooftop solar installation contributes to:
🌍 ~539 tons of CO₂ emissions avoided
🌳 ~633 trees planted (equivalent)
🏭 ~267 tons of coal burn avoided
🚗 ~2.12 million km of petrol consumption offset
A meaningful step towards sustainable and energy-efficient entertainment operations.